Titagarh Town
 
The scheme for Titagarh Town comprises
 
1. Renovation of existing MPS and STP's
   
2. Construction of Intercepting Sewers to divert the waste water presently discharged into the river Hooghly.
   
3. Construction of new Lifting Stations near the Out-falls of open drains for arresting and diverting DWF through intercepting sewers.
   
4.
Renovation of pail depots and improvement of flushing arrangements.
   
5. Interconnection of existing surface drains with existing and proposed sewers.
   
6. Renovation of existing trunk sewers and surface drains.
   
7. Construction of new MPS
   
8. Construction of new low cost STP.
 
Project Amount - 656.81 Lakhs